Exciting developments are taking place as backhaul work has officially commenced in Torquay!
A SUBCO-approved contractor has begun the essential route feasibility study for the installation of sub-ducts and optic fibre cables along the primary path from Torquay to Melbourne. A key part of this process is the field walk exercise, which aims to determine the availability of existing ducts. This step is crucial for ensuring that the installation proceeds smoothly and efficiently, making use of the current infrastructure wherever possible.
To identify duct availability, a technique known as rod and roping is employed. This involves verifying and feeding rope through new and existing conduits to facilitate the hauling of new fibre cables and reserving capacity.
In parallel with the rod and roping, the proving exercise has also commenced. This process includes a thorough examination of the ducts to confirm their suitability for the new optic fibre cables. By conducting these exercises simultaneously, we can expedite the overall project timeline.
Stats on the walk exercise so far:
Total Distance to be walked: 98,500m
Total Distance covered so far: 65,000m
Rod & Roped: 11,000m