SUBCO has officially begun its Horizontal Directional Drilling (HDD) construction effort in Adelaide.
Forming part of the Adelaide cable landing infrastructure, the 100mm ID HDD conduit will extend approximately 1000 meters from the shoreline and will break out under the surface at a depth of approximately 20 metres. For this HDD operation, a smaller pilot borehole is first drilled, and then enlarged to accommodate the final installed steel conduit in which the subsea cable will be installed at later date.
During drilling operations, the anticipated drill head speed equates to an HDD completion rate of around 96 metres per day. The HDD path may be straight or gradually curved, and the direction of the drilling head can be adjusted at any stage during the initial pilot bore to avoid detected subterranean obstacles.
As a part the early planning stage for a horizontal directional drill operation, a land-based survey of the route and a review of the near shore marine survey data was conducted to understand and minimise potential impacts. Part of this work involves marine ecology assessments, geotechnical investigations, service location works and potholing of existing assets.
The final HDD bore design allows for sufficient underground clearance to sensitive near shore marine environments, eliminating the risk of surface impact and ensuring that the HDD implementation meets project approval criteria.
Overall, we anticipate this part of the project to take around 12 weeks to complete.