A Big Year for the SMAP Project – 2024 Progress Recap 

This year has been monumental for the SMAP Project. Let’s take a look back at the highlights!  
 
The SMAP Blog officially launched in November 2023, documenting our progress and attracting almost 40,000 views since its inception.  
 
March 
  • Cable Manufacturing: Production began at ASN. 
  • System Upgrade: The SMAP cable’s design was enhanced from 12 to 16 fibre pairs, increasing total system capacity by 33%. This upgrade provides an increased total capacity from 300Tbps to 400Tbps, meeting surging demand connectivity. 
April 
  • Sydney Fronthaul: Construction commenced, moving the project forward. 
May 
June 
August 
  • Adelaide HDD Completion: Horizontal directional drilling (HDD) finished, paving the way for the beach manhole excavation and installation. 
September 
  • LEGO Model at AusNOG: We showcased a LEGO model of the SMAP Cable at AusNOG 2024.
  • Groundbreaking in Maroubra: Celebrations took place as HDD work officially began. Melbourne (Torquay) HDD is scheduled for 2025, with all landing infrastructure expected to be ready within the next 12 months. 
October 
November 
  • Backhaul Design: The Torquay to Melbourne backhaul design reached completion.
  • Repeater Progress: Subsea repeater manufacturing hit 100% completion.
  • Partnership with Google: SUBCO announced a collaboration with Google to develop critical landing infrastructure in Maroubra, NSW, and Torquay, VIC. This partnership aims to deploy connectivity solutions efficiently while minimizing environmental impact and strengthening Australia’s subsea cable routes. 
 
Looking Ahead 
  • Cable Manufacturing: Progressing well, with completion anticipated by year-end. Deployment is scheduled for mid-2025. 
 
 What a year it’s been for the SMAP Project. Here’s to even greater milestones in 2025. Scroll through some of our favourite images from this year below. 
 
 ​