In a major milestone for the SMAP project, we’re excited to announce that we’ve reached 100% manufacturing completion for the wet plant, including:
- 100% wet segment cable sections
- 100% repeaters, including spares
- 100% branching units, including spares
System Assembly is currently underway, and the SUBCO team will soon be heading to Calais to oversee the System Assembly & Tests (SAT) at the ASN manufacturing plant.
What is System Assembly & Tests?
This is the process undertaken at the factory to assemble all the system components into their final arrangement and carry out thorough testing and characterisation prior to loading onto the cable ship and then laying on the seafloor.
Tests are carried out to confirm the optical and electrical characteristics of each cable section, repeater and branching unit. These tests help ensure the optical power levels are within range, the electrical performance of the system is correct and that there are no cumulative issues across the assembled system.
It’s critical to demonstrate correct operation of the whole system prior to ship loading, and to catch and remediate any possible issues beforehand, as they may be much more expensive and problematic to fix later on.