We’re pleased to share a major progress update from the field, as cable lay for Segment 2A of the SMAP system ramps up off the coast of Perth.
The ASN cable ship Ile d’Yeu has successfully recovered the pre-laid shore end (PLSE) for Segment 2A, marking the start of critical subsea operations. The Initial Splice, the first connection between the shore-end cable and the cable trunk, has been completed and has been deployed to the seabed, clearing the way for the Main Lay phase to continue.
With that milestone reached, the Ile d’Yeu has launched the subsea plough – a specialist tool designed to trench and bury the cable beneath the seabed. This process is vital to protect the cable from external risks such as fishing activity, anchors, and natural seabed movement. The plough cuts a narrow trench, lays the cable into it in a controlled manner, and allows sediment to naturally settle over the top, ensuring secure long-term burial with minimal environmental disturbance.
Plough burial is now well underway, with 13 kilometres of cable successfully laid and buried to date. This marks a significant milestone in the delivery of next-generation digital infrastructure, connecting Western Australia to key international destinations.
Stay tuned for more updates as the install progresses over the next 6 months.