Segment commissioning underway

Alcatel Submarine Networks (ASN) has officially commenced segment commissioning on the western portion of SMAP, covering Perth, Adelaide and Torquay West.

In tandem, marine installation works between Sydney and Torquay East have now been completed – a major milestone for the project.

What is segment commissioning?

Segment commissioning is a comprehensive testing and characterisation process that validates the performance and integrity of each section of the system. This includes all fibre pairs, undersea bodies (repeaters and branching units), and station equipment.

Image (67)

Key activities include:

  • OTDR and COTDR measurements across all fibre pairs
  • OSNR and GOSNR performance measurements
  • Electrical characterisation and testing
  • Network Management System (NMS) commissioning
  • Branching Unit (BU) electrical and optical switch testing
  • Repeater interrogation
  • Confidence and stability trials

This rigorous process ensures each segment performs to specification before progressing to full system acceptance.

What happens next?

Once commissioning is successfully completed across all segments – and results are thoroughly reviewed to satisfaction – the full SMAP system will be formally handed over from ASN.

From there, SUBCO will deploy its transmission equipment and prepare the network to begin serving customers.

With commissioning now underway and marine installation complete across the remaining route, SMAP continues to move steadily toward RFS.