SMAP reaches provisional acceptance

After more than 1,000 days of surveying, manufacturing, installing, and testing, SMAP has reached provisional acceptance – the final validation milestone before the system is declared ready for service.

It’s a significant moment. Provisional acceptance confirms that Australia’s newest transcontinental subsea cable system has been independently tested and verified to specification across its full 5,000-kilometre route, connecting Sydney, Melbourne, Adelaide, and Perth.

Provisional acceptance is the point at which the system supplier – in SMAP’s case, Alcatel Submarine Networks – formally hands over a validated, fully commissioned system to the cable owner. It follows the completion of acceptance testing across every segment: optical performance, repeater characterisation, branching unit switching, and end-to-end system trials.

For SMAP, that process has been running in parallel with the final stages of terrestrial backhaul and SLTE integration across all four landing points. The system is now in its final phase before commercial launch.

With provisional acceptance confirmed, the focus now shifts to SLTE integration and final preparation for ready for service. SMAP’s RFS is targeted for June 2026.