Cable loading 100% complete

Last week we hit a major milestone for SMAP, with 100% completion of cable loading onto the ship before it sets sail for Australian shores. 

Quality Assurance/Field Services rep, Paddy Cunningham gives us an inside look at the process of getting over 5,000km of cable loaded, and life onboard the Île d’Yeu. 

“With SMAP manufacturing wrapped up, the next major milestone was the meticulous loading of the 5,200 km and 7,000 tonnes of subsea fibre optic cable onto the Île d’Yeu cable ship in Calais, France. Over 36 straight days, cable was spooled from massive factory storage containers, via a kilometre-long tunnel, into the ship’s cable tanks (whose total capacity is 5,900m³, or 2.3 Olympic swimming pools!). The operation was 24/7, with shifts operating around the clock to ensure the cable loading was efficient.

As SUBCO’s onboard rep, I lived aboard the vessel alongside the 65 other crew members for the duration of the operation, to ensure quality compliance and to witness and sign off on the successful loading of the 60 in-line repeaters as well as the branching units, shape equalisers and all system spares. There was a mess hall, common room, satellite internet and laundry – making it quite a self-contained setup.

Everyday there would be a meeting conducted, where the distance of cable loaded in the previous 24 hours was reported (down to the metre), and the logistics of the coming days were discussed. The progress report also included timestamps of any loading pauses and the exact distance at which a cable inspection occurred.  

After each segment was loaded, a team of specialised testers carried out optical and electrical checks on the fibre to confirm it was performing correctly and had sustained no damage during loading. In the final days, similar tests were conducted on all branching units and spare components to verify their functionality before departure.

Now that loading is completed, the ship is enroute from Europe to Australia on a 49-day journey stopping in Cape Verde (off West Africa) and Cape Town for supplies and crew changes, before arriving in Perth to begin the 6-month SMAP cable laying.”