CLS installation commences in Perth

The design for our Perth Cable Landing Station (CLS), housed within an existing data centre, was finalised last year, and is now underway.

The CLS occupies approximately 40 square meters within the data centre, benefiting from all the “comforts of home”—including dual UPS and generator-backed electrical distribution systems, dual power feeds to every rack position, redundant cooling, humidity control, aspirated smoke detection, and fire suppression.

Like our own facilities, the site has robust security measures in place, and we’re further enhancing them by implementing additional security controls—right down to the rack level.

Our team is set to be on-site in early April to complete the internal fit-out, ensuring everything is ready for ASN to begin installing the subsea power and transmission equipment.