Final splice completed

On 1 April 2026, in the Bass Strait off Torquay, the SMAP final splice was completed – marking the end of nine months of marine installation.

Segment 2D: the last link

The final splice closed out Segment 2D – a short but critical section of cable in the Bass Strait connecting the two branching units either side of Torquay. The West End of the cable had been resting on the seabed for approximately a month following the previous lay campaign. Our team recovered it early on the morning of 1 April, bringing both cable ends aboard simultaneously.

Pre-splice testing

Before any cutting begins, both cable ends go through a two-stage test regime. First, optical testing – verifying every fibre against its baseline performance to confirm no degradation during the seabed soak. Second, an insulation resistance (IR) test – an electrical check of the power feeding conductor to confirm the high-voltage DC element is performing to spec. The West End was held under controlled tension by the vessel’s Linear Cable Engine (LCE) throughout. Both tests cleared before the splice could begin.

Cable preparation

With testing complete, both ends were prepared for jointing – outer armour layers, bedding, and insulation removed sequentially to expose the fibre bundles. Both ends were then cleaned, measured, and fitted with the external anchor assemblies that form the structural housing of the joint. From the start of cable prep to the first splice: approximately eight hours.

The splice

SMAP carries 32 fibre pairs across its trunk. Each fibre is spliced individually in the vessel’s joint bay under controlled conditions, using fusion splicing equipment to produce a low-loss, mechanically protected joint.

The moment the first fibre fused, there was a single contiguous optical path from Sydney to Melbourne, Adelaide, and Perth. The remaining 31 splices followed through the day, with all 32 complete by 9:00 PM.

Once all fibres were spliced, they were carefully coiled around the central former inside the joint housing and the joint was sealed. At that point, onboard testing is no longer possible — the system is closed.

End-to-end system testing

With the joint sealed, we deployed teams simultaneously to the Sydney Cable Landing Station and the Perth Cable Landing Station to perform end-to-end trunk testing across the full length of SMAP. Validating the final splice and confirming the system was performing to specification.

The final bight

On the afternoon of 2 April, the joint box was lifted by crane and the final loop of cable – the final bight – was paid out over the stern. As the joint box and cable loop descended to the seabed, all 5,000 kilometres of SMAP were in the water.

SMAP is now in system completion, with acceptance testing underway ahead of RFS.