VicTrack backhaul progress

Last month we announced a partnership with the Victorian Government and VicTrack, to construct a fibre network along the Melbourne – Geelong rail corridor. Over the past couple months, the team have worked through challenging terrain, permitting, environmental considerations and extensive local stakeholder engagement – and the progress speaks for itself.

To date, 80km of the 87km backhaul route has been walked, meaning our field teams have now physically verified more than 92% of the alignment. This validation gives us strong confidence in constructability and land-access planning.

We’re also pleased to report that 74km has now been rodded and roped, clearing the way for fibre installation with greater certainty and minimal rework.

In parallel, 38km of design has been completed and submitted, supporting sequencing and construction planning across multiple segments of the route.

A huge thank-you to CableNet, FTS Resolve and their permitting consultants for their continued commitment and excellent work.