VicTrack backhaul update

VicTrack back haul works along the Melbourne – Geelong rail corridor continues to make progress. Almost 85km of the 87km route has been walked and verified, 81km has now been rod and roped, and 50km of design has been completed and submitted, supporting sequencing and construction planning.

Field Team 2
Field Team
Cablenet Working In Rail

Our delivery partners, CableNet Industries and FTS Resolve, have been working closely with Rail Operations and Safeworking (ROS) as we progress design, construction and safety planning for the backhaul network. Through early collaboration and strong governance, the works are aligned with rail authority requirements to support efficient and compliant high quality submission packs for approval with VicTrack, V/Line, Australian Rail Track Corporation (ARTC) and Metro Trains Melbourne. This ensures alignment with track safety requirements, coordination and technical inputs across fibre, civil and installation disciplines.