Maroubra fronthaul work in final stages

We’re now at the final stages of the fronthaul work in Sydney. We are currently on track to be complete at the end April.

Our current progress on the work as stands today..

49 / 52 (94%) Manhole Installations
7,625m / 8,279m (92%) of duct Installation
77,030m / 91,102m (84%) of Sub-Duct Installation

Understandably there has been a lot of work in the area, and we’re appreciative of the council and surrounding communities working with us.