SMAP EOY update

Over the past quarter, SMAP has continued to advance across land and sea, with Adelaide and Torquay CLS fit outs progressing, backhaul mobilised, and the successful landing of Victoria’s very first subsea cable. Over 55% of the subsea cable is installed and the build is now at 85% overall completion. 

Here’s a wrap-up of the project for this quarter: 

Adelaide: CLS and backhaul progress

The Adelaide CLS fit-out and subsea infrastructure are now complete. This includes the installation of ASN’s Power Feeding Equipment (PFE), which supplies high-voltage DC power to subsea repeaters – critical for long-distance data transmission. Transmission network deployment will commence early next year as preparations for RFS continue.

Backhaul mobilisation began in October, connecting the CLS to Adelaide’s CBD via two diverse terrestrial fibre routes. The civil buil, covering approximately 8km, is complete, and the remaining network is currently being proven. The next phase will see the installation of around 30km of fibre.

Torquay: First subsea cable for Victoria

In Torquay, all major infrastructure for the cable landing has been completed. This includes the horizontal directional drilling (HDD), with two bore pipes extending from the beach manhole near Point Danger out to sea, as well as the fronthaul connection back to the CLS and the subsea cable itself.

Following the successful cable landing, the HDD beach manhole site has now been handed back for community use and environmental restoration, a major milestone for both the project and the region.

The Torquay CLS fit-out is nearing completion, with final ASN equipment installation underway. Transmission network works will continue into next year.

Backhaul and regional connectivity

Progress is also being made on the Melbourne-Torquay backhaul, with 50% of the 100km primary route installed and completion expected next quarter.

In addition, SUBCO announced a partnership with VicTrack and the Victorian Government to deliver a secondary terrestrial fibre route along the Melbourne–Geelong rail corridor, strengthening network resilience and boosting regional connectivity.

Marine installation update

Marine installation continues at pace, with more than 55% of the SMAP subsea cable and repeaters now installed. Deep-water installation from Perth to Adelaide is complete, along with both the Adelaide and Torquay branches.

Industry recognition

This quarter also brought global recognition, with SMAP awarded “Best Subsea Innovation” by Capacity Media at the Global Connectivity Awards in London.

What’s next

The focus for the coming months includes:

  • Completion of the Torquay CLS
  • Adelaide and Melbourne backhaul completion
  • Transmission installation across all sites
  • Final marine installation
  • System completion, including acceptance testing and integration

All roads lead to getting SMAP ready for service!