Backhaul cable install at Torquay CLS complete

Progress continues on the terrestrial backhaul infrastructure, with the cable installation into the Torquay CLS now completed. Our teams are currently undertaking cable terminations to prepare for the next stages of network integration. This milestone builds on earlier civil and conduit works and brings us closer to completing the terrestrial links needed for full connectivity.

At the M3 site, the lead‑in conduit connection has been successfully completed. This crucial pathway will accommodate the next segment of cable, scheduled for installation next week, and connects our backhaul infrastructure into the broader terrestrial network.

Across the backhaul network, final splicing activities are in progress. These splices join cable segments to enable continuous and resilient fibre connectivity between key points on the SMAP route.

With installation and splicing advancing, we’re targeting end-to-end testing to commence in the week starting 23 February. This phase will validate connectivity and performance across the terrestrial backhaul links ahead of full network integration.

Stay tuned for further updates as we progress toward final commissioning and deliver next‑generation connectivity across Australia.