Final repeater deployed – marine install nearing finish line

SMAP marine installation has hit a landmark milestone with all 59 repeaters now in the water!

With deployment of the final repeater, attention now turns to the final steps of marine installation. Next up is the Branching Unit (BU) integration at Torquay – connecting Melbourne (Torquay) and Sydney via the Torquay East X-BU – followed by the final splice to bring the full subsea route together.

Once marine install wraps and commissioning is completed across all segments, the system will be formally handed over from Alcatel Submarine Networks (ASN), ready for SUBCO to deploy its transmission equipment and prepare the network for service.