Facilities Test Environment Set Up

Testing

As part of the ongoing development of SMAP, our team of engineers have started to test various networking and facility management components thanks to a mock ‘lab’ set up in the SUBCO office.

Security is paramount when it comes to the design of this system, so this testing process is key to ensure we have the right equipment in place prior to deployment, and that we have a standardised deployment for our sites.

Here’s a snapshot of what we are testing:

  • Electronic rack locking and alarming for security (physical security for the racks)
  • Integration of alarms and CCTV cameras to optimise our NOC’s response to on-site events
  • Integration of intercoms with the CCTV system to streamline site attendance
  • Internal and external camera and surveillance technologies
  • Wide 800mm racks (600mm wide is standard) to allow for improved cable management in fibre dense transmission racks
  • Improved telephony options to optimise communications from sites that may otherwise have poor mobile coverage, and enhance the experience for technical staff working from these sites
  • Positioning of hardware and cabling in the racks so that we have this planned in advance rather than solving basic problems “on the day”
  • Integration of devices into our network management systems to ensure we can properly monitor and collect telemetry from them 

The testing phase gives us insight into how we deploy infrastructure to support the SMAP cable and will also assist with planning upgrades at other SUBCO locations, improving the operation of the entire network.