System Assembly 30% completion

System.assemble

With Manufacturing tracking well, we’re excited to report that we have hit 30% completion of the System assembly. The System Assembly & Tests consists of the steps required to combine the system components in order to verify and document the performance of the system, first at the “block” level and finally at the whole of system level in the factory prior to ship loading.

When the cable system components are manufactured, including the: cable sections, repeaters, branching units and terminal equipment, they are first joined into so-called “blocks” consisting of a certain number of contiguous cable sections and their associated repeaters (roughly every 18 repeaters in the case of SMAP).  The gain flatness and tilt for the block are then measured to identify any accumulated gain shape or tilt variations outside required thresholds. Whilst each repeater already has its own “Gain Flattening Filter”, minor variations in individual repeater gain shape or tilt can accumulate after numerous repeaters and need to be corrected by the periodic insertion of shape and/or tilt equalisation filters.

Once all the blocks are confirmed and corrected, the whole of the system is assembled in the factory and extensive tests are carried out to verify all system functions and performance prior to ship loading.  The lists of tests required is quite large but includes things like:

  • Verify operation of all system power configurations and associated power switching, e.g.
    • Double & single end feeding from each end
    • Branch power configurations
  • Verify system operating voltages at nominal system current
  • Verify transmission performance across each optical path, including:
    • Gain shape and tilt
    • Optical signal-to-noise ratio (OSNR)
  • Verify active branching unit command response for all optical and/or power switching functions

Block assembly and testing continues as manufacturing proceeds and we are looking forward to completion of manufacturing and full system assembling tests early next year.