Torquay HDD work complete and ready for returfing

We’re pleased to share that the Horizontal Directional Drilling (HDD) works at Voss Circuit (Torquay) have been successfully completed, and the site was officially handed back to GORCAPA on 26 September 2025.

Over the coming weeks, GORCAPA will carry out returfing and site restoration, preparing the reserve to reopen ahead of the busy summer season. This will ensure the community can continue to enjoy the area with minimal long-term impact from the project.

Works at Voss Circuit began on 19 May 2025 and were completed on 26 September 2025, spanning 131 days. The team successfully installed 2,400 metres of HDD beneath the reserve, completing the drilling during the winter months as planned to minimise disruption to local residents, reserve users, and the wider community.