We’re pleased to share a major progress update from the field, as cable lay for Segment 2A of the SMAP system ramps up off the coast of Perth. The ASN cable ship Ile d’Yeu has successfully recovered the pre-laid shore end (PLSE) for Segment 2A, marking the start of critical subsea operations. The Initial Splice, […]
Category Archives: Uncategorized
SUBCO team members Matt, Paddy, Joseph and Founder & Co-CEO Bevan are currently attending SubOptic 2025 in Lisbon, joining global leaders from across the subsea cable industry to explore the future of international connectivity. Held at the Lisbon Congress Centre, the event brings together experts, innovators, and policymakers to discuss the challenges and opportunities shaping […]
SUBCO, represented by Lee Harper, Carlos Trujillo, Bob Purdon, Matt Clancy, and Brendan Reddy, participated in the SMAP Contract Coordination Meeting (CCM) held in Sydney. Key stakeholders in attendance included representatives from ASN and OMS. The two-day event followed the standard CCM agenda. On the second day, attendees visited key project sites, including the Sydney […]
SUBCO has reached a major milestone in the SMAP subsea cable project, completing horizontal directional drilling (HDD) at Broadarrow Reserve in Maroubra. The time-lapse video captures weeks of engineering precision, community collaboration, and logistical coordination — condensed into 30secs. This stage of the project involved: Six successful horizontal directional drills, enabling safe and environmentally conscious […]
Recently, two of our team members – Rick Carter and Bob Purdon were on the ground in Perth working on the buildout of our first Data Centre site. With a tight schedule, multiple contractors, and a lot of hardware to install, it was a fast-paced and rewarding experience. In this post we take a bit […]
The commencement of one of the most critical phases of any submarine cable system is the loading of the cable ship — and for the SMAP project, it marked a major milestone in bringing our vision to life. This carefully controlled and precise loading operation is expected to continue until mid-May. Here is an insight […]
We’re excited to share that the horizontal directional drilling (HDD) works at Broadarrow Reserve have been successfully completed, and the area has now been handed back to Randwick City Council and the local community. This marks a major milestone in our project, concluding a key phase of work delivered in partnership with UEA Pty Ltd. […]
We’re excited to announce a major milestone in the journey of our upcoming subsea cable project – the planning permit for our Cable Landing Station (CLS) at West Beach (Adelaide) has officially been approved. This approval marks a significant step forward in delivering world-class digital infrastructure, enhancing connectivity, capacity, and resilience for our customers and […]
Over the past few weeks, UGL has been progressing through one of the more challenging sections of the Fronthaul conduit installation. The area presents significant complexity due to the dense concentration of existing underground services and consistently high traffic volumes. As a result, all works have been carried out at night in close coordination with […]
We’re excited to share that we embarking on an independent journey, breaking away from our parent company, SODA. This marks a pivotal moment for our team, our customers, and the industry as we continue on our mission to build world-class submarine cable infrastructure. History has shown that great things happen when ambitious companies step out […]