Recently, we had the pleasure of signing off on the sixth and final HDD required for the Sydney (Maroubra) Landing. As mentioned in previous posts, the accuracy and precise measurements are critical before each HDD sign-off to ensure a smooth installation when the cable arrives later this year. This marks a significant milestone for the […]
Monthly Archives: March 2025
With the design finalised and approvals imminent, construction of our Adelaide Cable Landing Station is set to begin later this month. Originally designed to house just the Power Feed Equipment (PFE) and optical switching for backhaul to third-party data centres, the facility has now been expanded to accommodate Submarine Line Terminal Equipment (SLTE) deployment if […]
The design for our Perth Cable Landing Station (CLS), housed within an existing data centre, was finalised last year, and is now underway. The CLS occupies approximately 40 square meters within the data centre, benefiting from all the “comforts of home”—including dual UPS and generator-backed electrical distribution systems, dual power feeds to every rack position, […]
We’re now at the final stages of the fronthaul work in Sydney. We are currently on track to be complete at the end April. Our current progress on the work as stands today.. 49 / 52 (94%) Manhole Installations 7,625m / 8,279m (92%) of duct Installation 77,030m / 91,102m (84%) of Sub-Duct Installation Understandably there […]
Construction has officially begun at our Torquay CLS site, with the site cut now in progress. Over the next eight months, we will be building this critical infrastructure, marking another major milestone in the SMAP project. A huge thank you again to our team for their dedication and hard work in bringing this project to […]