As we reach the mid-way point of 2025, SMAP continues to gain momentum, moving from planning and preparation into full-scale execution. This year has been marked by major achievements across regulatory approvals, system design, construction milestones, and now, the critical start of marine cable installation with the successful cable landing in Perth last week. With […]
Monthly Archives: June 2025
Construction of the front haul network is now underway in Torquay, marking an important milestone for the project. Our contractor UGL Pty Ltd has commenced groundworks following the successful completion of land access negotiations with relevant stakeholders, including property owners, local council and utility providers. This collaboration has ensured that all necessary approvals […]
This week marked a major moment for the SMAP project, with the successful shore-end landing of the cable system in Perth. The OMS shore-end and dive support teams were on site early to prepare for the landing. With the beach manhole and existing infrastructure ready, final checks were carried out on the seaward-facing conduit, which […]
Exciting progress continues at the Torquay Cable Landing Station, with a significant milestone now achieved – the installation of all 49 internal and external walls, along with 38 hollow-core roof planks. This marks a pivotal step forward in the construction phase, as the facility begins to take on its final structural form. The installation of […]
The Adelaide Cable Landing Station is now taking shape with another milestone reached with competition of the slab construction. Our building contractor, Sagle, has worked diligently to bring us to this stage of the project. While the completed slab may appear minor at first glance, it represents a significant milestone – the successful completion […]
SUBCO team members Matt, Paddy, Joseph and Founder & Co-CEO Bevan are currently attending SubOptic 2025 in Lisbon, joining global leaders from across the subsea cable industry to explore the future of international connectivity. Held at the Lisbon Congress Centre, the event brings together experts, innovators, and policymakers to discuss the challenges and opportunities shaping […]
Last week we hit a major milestone for SMAP, with 100% completion of cable loading onto the ship before it sets sail for Australian shores. Quality Assurance/Field Services rep, Paddy Cunningham gives us an inside look at the process of getting over 5,000km of cable loaded, and life onboard the Île d’Yeu. “With SMAP manufacturing […]