Tag Archives: Cable

Final repeater deployed – marine install nearing finish line

SMAP marine installation has hit a landmark milestone with all 59 repeaters now in the water! With deployment of the final repeater, attention now turns to the final steps of marine installation. Next up is the Branching Unit (BU) integration at Torquay – connecting Melbourne (Torquay) and Sydney via the Torquay East X-BU – followed […]

Final testing at Torquay CLS & Melbourne DC underway

Construction may be finished, but before a system is declared ready for service, every fibre must pass rigorous validation. We’re now conducting final bi-directional Optical Time-Domain Reflectometer (OTDR) testing to ensure the entire span is performing exactly as engineered. OTDR testing allows us to measure fibre attenuation, splice integrity, and identify any reflections or anomalies […]

Segment commissioning underway

Alcatel Submarine Networks (ASN) has officially commenced segment commissioning on the western portion of SMAP, covering Perth, Adelaide and Torquay West. In tandem, marine installation works between Sydney and Torquay East have now been completed – a major milestone for the project. What is segment commissioning? Segment commissioning is a comprehensive testing and characterisation process […]

Backhaul cable install at Torquay CLS complete

Progress continues on the terrestrial backhaul infrastructure, with the cable installation into the Torquay CLS now completed. Our teams are currently undertaking cable terminations to prepare for the next stages of network integration. This milestone builds on earlier civil and conduit works and brings us closer to completing the terrestrial links needed for full connectivity. […]

Final SMAP cable landing complete

This week marked a significant milestone for Australia’s digital infrastructure, with the final SMAP cable landing successfully completed at Maroubra. From the Ile d’Yeu offshore, the SMAP cable was winched through approx 1.2km of horizontal directional drilling (HDD) to the beach manhole at Broadarrow Reserve. The landing is the result of months of planning, collaboration, […]

Adelaide backhaul hauling underway

Backhaul cable hauling has officially commenced in Adelaide, marking another important milestone in the delivery of the SMAP cable system. Working alongside partner Mirait Technologies Australia, the team began hauling the first sections of backhaul cable this week, connecting the Adelaide cable landing station into the broader terrestrial network. This phase brings the system one […]

Adelaide branching unit deployed

Our first update of 2026 is no small feat with the successful deployment of SMAP’s first X-BU at the Adelaide branch. The X-BU is a next-generation branching unit designed to integrate both electrical and optical switching sea cases into a single wet body for high fibre count systems, such as SMAP’s 16 fibre pairs. This […]

SMAP EOY update

Over the past quarter, SMAP has continued to advance across land and sea, with Adelaide and Torquay CLS fit outs progressing, backhaul mobilised, and the successful landing of Victoria’s very first subsea cable. Over 55% of the subsea cable is installed and the build is now at 85% overall completion.  Here’s a wrap-up of the project for this quarter:  Adelaide: CLS and backhaul progress The Adelaide CLS fit-out […]

SMAP cable makes landfall in Torquay

This week, the Ile d’Yeu successfully landed the eastern segment of the cable in Torquay, which will eventually connect to Sydney. Weather permitting, the team will land the western segment this week which will link all the way to Perth. To achieve this with minimal environmental impact, engineers installed two bore pipes running from a […]

Marine update – 50% of cable installed

The SMAP marine lay is progressing well, with more than 50% of the total cable length and repeaters now installed. This marks a major milestone in the build of Australia’s new east–west subsea connection. Following successful deep-water installation from Perth to Adelaide, plough burial has now commenced on the Adelaide branch. This process carefully embeds […]