On Friday, our team successfully completed the Pre-Lay Shore End (PLSE) landing for the SMAP cable in South Australia. A major milestone as the state’s first ever subsea cable comes ashore. Captured in this video, the PLSE operation involved carefully bringing the cable through HDD (horizontal directional drilling) works where it will then be connected […]
Tag Archives: Cable
On Friday 11 July, SUBCO had the honour of hosting the WA Premier, the Honourable Roger Cook; Minister for Resources, the Honourable Madeleine King; and the local Member for Cockburn, David Scaife MLA, for a tour of the mighty ASN cable-laying vessel Ile d’Yeu in Perth. We were also pleased to welcome industry friends, partners, […]
Big things are happening off the coast of Perth! The mighty Ile d’Yeu is en route to deliver Australia’s very first undersea hypercable, SMAP. Originally built as a pipelayer back in 2001, Ile d’Yeu has since had a high-tech makeover, transforming into a top-tier cable-laying ship capable of installing some of the most advanced transoceanic […]
This week marked a major moment for the SMAP project, with the successful shore-end landing of the cable system in Perth. The OMS shore-end and dive support teams were on site early to prepare for the landing. With the beach manhole and existing infrastructure ready, final checks were carried out on the seaward-facing conduit, which […]
Last week we hit a major milestone for SMAP, with 100% completion of cable loading onto the ship before it sets sail for Australian shores. Quality Assurance/Field Services rep, Paddy Cunningham gives us an inside look at the process of getting over 5,000km of cable loaded, and life onboard the Île d’Yeu. “With SMAP manufacturing […]
The SMAP cable system will have over 5200km of subsea cable across its trunk (Sydney to Perth) and branches (Melbourne and Adelaide). We’ve looked briefly before at cables and repeaters, but since our manufacturing is approaching 100% completion, today we’re going to do a deep dive into how a submarine cable is made. A […]
Manufacturing of SMAP’s 61 repeaters has been completed, signalling a major milestone in the production of the cable system. During the manufacturing of the repeaters, over 25,000 tests/checks were carried out to ensure they meet specified performance criteria. Each repeater is placed 90km apart over the length of the cable and extensive testing and qualification […]
PFE: For Perth , Sydney, Adelaide and Torquay have been manufactured & tested Cable: 38% of the cable has been completed, with 2042 km out of 5265 km manufactured Repeaters: 71% completion, with 43 out of 60 repeaters manufactured and tested Branching Units: No progress yet on the manufacturing of Branching Units We also conducted a […]
SMAP is poised to make waves in pioneering Australia’s first sully armoured subsea cable, representing a significant advancement in safeguarding critical communication infrastructure. The fully armoured design, adapted with varying levels of protection along different sections of the cable, offers unparalleled protection against potential threats and unplanned outages. Double Armour (DA) (pictured) adds two layers […]
As a Project manager for SUBCO, Dan Wright plays a pivotal role in overseeing multiple components of the SMAP build. His primary focus is on designing routes, managing the construction of both ocean outfalls and routes, and handling stakeholder management with key partners involved in the cable’s construction. With eight years of experience in the […]