Monthly Archives: August 2024

Torquay CLS design signed off and scheduled for construction

Torquay CLS Station Render Approved

The design for our Torquay Cable Landing Station (CLS) has officially been approved and is scheduled to commence construction in the coming months. With a facility size of 258 square meters, the cable landing station comprises of 2 independent rooms, each equipped with its own uninterruptible power supply (UPS) and cooling systems. Plus, two un-interrupted […]

Adelaide Manhole Installed

Manhole progress | SUBCO SMAP Blog

We’re excited to report that the beach manhole component in Adelaide has been completed.  Over the past 70 days, our construction partner CODMAH has put in significant effort to complete the challenging ocean lead-in, culminating in the installation of our custom-designed beach manhole. The ocean lead-in is a crucial segment of the cable route that […]

Navigating New Depths: A Year of Progress on Subco’s SMAP Project – With Bevan Slattery

Year.update.slattery

As we reach the one-year mark on the SMAP project, we sat down with Bevan to get his perspective on the last twelve months and an insight into what’s on the horizon. “I’m excited to share some key updates. It’s been a busy and challenging year, with this project standing out due to its scope […]

Understanding Undersea: Torquay Landing to create a diverse connection into Melbourne CBD

SUBCO’s decision to establish a cable landing point in Torquay as part of the SMAP cable route heralds a significant development in bolstering connectivity between Torquay and Melbourne. By creating a diverse connection route, this strategic move enhances the resilience and reliability of communication networks through Geelong to the coast. Torquay’s coastal location further offers […]

Melbourne Backhaul survey and rod and roping complete

Torquay.backhual.blog

A few weeks ago, we embarked on a critical assignment to assess the existing ducts for our planned route between Melbourne and Torquay. As we’ve emphasised before, our commitment to minimising environmental and community impact guides every decision we make, ensuring we always opt for the most efficient solutions. With the survey and rod and […]

Adelaide preparing for Beach Manhole excavation

Adelaide.hdd.completion

After a successful HDD completion, the team is now dismantling the rig in preparation for the Beach Manhole excavation works. Over the past week, we completed the final steps to conclude the HDD. These included verifying the offshore HDD exit with divers, testing and installing the messenger rope, which will ultimately be used to draw […]

Adelaide drilling component has been completed

Great news from Adelaide! We have successfully completed the horizontal drilling component at the landing site, achieving a total distance of just over 1,000 meters. The next step is to verify the offshore HDD Exit with the diving team. The video above shows a timelapse of the drilling that took place in Adelaide. The HDD […]