Tag Archives: Cable Landing Station

Adelaide backhaul complete

SMAP’s backhaul network connecting the Adelaide CLS to the CBD is now complete, with final testing and commissioning well underway. Connecting the subsea and terrestrial networks, this milestone completes the end-to-end infrastructure chain that underpins SMAP’s connectivity offering in South Australia. With backhaul now in place, SMAP’s Adelaide infrastructure is ready for final system testing […]

Final testing at Torquay CLS & Melbourne DC underway

Construction may be finished, but before a system is declared ready for service, every fibre must pass rigorous validation. We’re now conducting final bi-directional Optical Time-Domain Reflectometer (OTDR) testing to ensure the entire span is performing exactly as engineered. OTDR testing allows us to measure fibre attenuation, splice integrity, and identify any reflections or anomalies […]

Victoria connects to the SMAP network

SMAP continues to gather momentum, with the Victorian Government announcing its support for the new subsea hypercable that will directly connect Victoria to Australia’s next-generation digital backbone and beyond. As part of the Sydney-Melbourne-Adelaide-Perth (SMAP) system, this development marks a major step in extending world-class connectivity to Victoria’s south coast. The project will see two […]

Torquay CLS gears up with final ASN equipment delivery

The Torquay CLS continues to take shape following the final delivery of Alcatel Submarine Networks (ASN) equipment. In total, just over 6 tonnes of Power Feeding Equipment (PFE) will be installed at the site, marking a major milestone in preparing the station for the SMAP cable. Installation of the PFE has now commenced, ensuring the […]

ASN equipment installed at Adelaide CLS

The ASN team recently completed installation of the Power Feeding Equipment (PFE) for the SMAP cable at our Adelaide CLS.   This equipment is a pivotal operational component of the system, and a major step closer to go-live for the project. PFEs provide constant high-voltage DC power to subsea repeaters, ensuring data travels reliably across thousands […]

Adelaide CLS fit-out nears completion

After the successful fit-outs of our Cable Landing Stations (CLS) in Perth and Sydney, our team set out once again—this time to Adelaide. With lessons learned from previous projects and a refined approach, we were ready to take on the next challenge. We’re back with SUBCO Senior Network Engineer – Rick Carter, who gives us […]

Torquay fronthaul civils complete

All civil conduit and manhole works have now been successfully completed in Torquay, between the beach manhole and the cable landing station. The final stage of subduct installation is currently underway, marking one of the last key steps before we can transition into the next phase. This achievement is the result of months of coordinated […]

Adelaide CLS lock-up complete

The Adelaide cable landing station at West Beach has now reached the lock-up stage, a significant step forward in our build program. With the external structure, internal utilities and facility now secure, the project is moving confidently into the next phase of internal fitout to prepare for operational readiness. A huge thank you to our […]

Adelaide fronthaul network complete

Adelaide fronthaul works have been successfully completed, another major milestone in the rollout of SMAP. ​ ​Delivered by our trusted contractor, Mirait Technologies Australia, the installation included five manholes and associated conduit. This infrastructure forms part of the fronthaul pathway that directly links to the Adelaide CLS. ​ ​The site was managed with appropriate traffic […]