On 1 April 2026, in the Bass Strait off Torquay, the SMAP final splice was completed – marking the end of nine months of marine installation. Segment 2D: the last link The final splice closed out Segment 2D – a short but critical section of cable in the Bass Strait connecting the two branching units […]
Tag Archives: Marine
SMAP marine installation has hit a landmark milestone with all 59 repeaters now in the water! With deployment of the final repeater, attention now turns to the final steps of marine installation. Next up is the Branching Unit (BU) integration at Torquay – connecting Melbourne (Torquay) and Sydney via the Torquay East X-BU – followed […]
Alcatel Submarine Networks (ASN) has officially commenced segment commissioning on the western portion of SMAP, covering Perth, Adelaide and Torquay West. In tandem, marine installation works between Sydney and Torquay East have now been completed – a major milestone for the project. What is segment commissioning? Segment commissioning is a comprehensive testing and characterisation process […]
SMAP’s Torquay West branching unit (X-BU) has successfully made it into the water, marking another step closer to RFS for Australia’s first hypercable. The successful install connects Torquay with Adelaide and represents months of planning, coordination, and precision engineering, ensuring the cable is perfectly positioned for its next stage of deployment. The X-BU is a […]
Our first update of 2026 is no small feat with the successful deployment of SMAP’s first X-BU at the Adelaide branch. The X-BU is a next-generation branching unit designed to integrate both electrical and optical switching sea cases into a single wet body for high fibre count systems, such as SMAP’s 16 fibre pairs. This […]
This week, the Ile d’Yeu successfully landed the eastern segment of the cable in Torquay, which will eventually connect to Sydney. Weather permitting, the team will land the western segment this week which will link all the way to Perth. To achieve this with minimal environmental impact, engineers installed two bore pipes running from a […]
SMAP continues to gather momentum, with the Victorian Government announcing its support for the new subsea hypercable that will directly connect Victoria to Australia’s next-generation digital backbone and beyond. As part of the Sydney-Melbourne-Adelaide-Perth (SMAP) system, this development marks a major step in extending world-class connectivity to Victoria’s south coast. The project will see two […]
The SMAP marine lay is progressing well, with more than 50% of the total cable length and repeaters now installed. This marks a major milestone in the build of Australia’s new east–west subsea connection. Following successful deep-water installation from Perth to Adelaide, plough burial has now commenced on the Adelaide branch. This process carefully embeds […]
South Australia has officially marked the beginning of its first-ever subsea cable, with the arrival of the world’s largest-capacity cable laying vessel, Ile d’Yeu, in Port Adelaide. Premier Peter Malinauskas joined SUBCO Founder and CEO Bevan Slattery to welcome the vessel, which will begin construction on the $400 million, 5,000 km SMAP system. Premier Malinauskas […]
Ile d’Yeu is continuing its progress towards Adelaide, with a long ~2,400km stretch of deep-water surface lay to complete, all in Lightweight Protected cable – read more about the different protection types used for SMAP linked here. Once she reaches the planned Adelaide branching unit location, she’ll bouy off the cable and carry out a […]