On Friday 11 July, SUBCO had the honour of hosting the WA Premier, the Honourable Roger Cook; Minister for Resources, the Honourable Madeleine King; and the local Member for Cockburn, David Scaife MLA, for a tour of the mighty ASN cable-laying vessel Ile d’Yeu in Perth. We were also pleased to welcome industry friends, partners, […]
Tag Archives: Marine
Big things are happening off the coast of Perth! The mighty Ile d’Yeu is en route to deliver Australia’s very first undersea hypercable, SMAP. Originally built as a pipelayer back in 2001, Ile d’Yeu has since had a high-tech makeover, transforming into a top-tier cable-laying ship capable of installing some of the most advanced transoceanic […]
This week marked a major moment for the SMAP project, with the successful shore-end landing of the cable system in Perth. The OMS shore-end and dive support teams were on site early to prepare for the landing. With the beach manhole and existing infrastructure ready, final checks were carried out on the seaward-facing conduit, which […]
Following last week’s site meet-up with Google, SUBCO are thrilled to announce the successful completion of HDD #2! Our delivery partner UEA have been making great progress, the video below illustrates divers finalising HDD #1 in Maroubra. During this process, precise measurements were taken to confirm positioning, including:• The distance from the seabed floor to […]
Big news! All marine surveys have now been completed, marking a significant milestone for the SMAP build. We’re one step closer to delivering the next generation of undersea connectivity, designed for the future – driving a more connected Australia. As it stands, the SMAP Project Overall is 26% complete.
The Bold Explorer has completed the deep-sea survey journey from Perth to Adelaide, Melbourne, and Sydney. With over 5,000 nautical miles covered, we’ve been analysing seafloor sediments to determine the best path for the cable and assess seabed stability to prevent future movement or damage. Additionally, we evaluate the marine ecosystem to minimise our environmental […]
Final consents and permits have been put in place for the Marine Survey component of the project. Over the past 6 months, SUBCO and its consultants have completed extensive Stakeholder consultations with Commonwealth and State based agencies in relation to the overall project and the specifics around the Marine Survey. The process included: Project briefings, […]