After the successful fit-outs of our Cable Landing Stations (CLS) in Perth and Sydney, our team set out once again—this time to Adelaide. With lessons learned from previous projects and a refined approach, we were ready to take on the next challenge. We’re back with SUBCO Senior Network Engineer – Rick Carter, who gives us […]
Monthly Archives: September 2025
Team SUBCO are on the ground in Singapore for Submarine Networks World held at the Sands Expo & Convention Centre. This is one of the premier global gatherings for the subsea communications industry – bringing together over 1,000 attendees, 130+ speakers, and many of the world’s leading submarine-network players, vendors, and decision makers. Yesterday, our […]
South Australia has officially marked the beginning of its first-ever subsea cable, with the arrival of the world’s largest-capacity cable laying vessel, Ile d’Yeu, in Port Adelaide. Premier Peter Malinauskas joined SUBCO Founder and CEO Bevan Slattery to welcome the vessel, which will begin construction on the $400 million, 5,000 km SMAP system. Premier Malinauskas […]
All civil conduit and manhole works have now been successfully completed in Torquay, between the beach manhole and the cable landing station. The final stage of subduct installation is currently underway, marking one of the last key steps before we can transition into the next phase. This achievement is the result of months of coordinated […]
The Adelaide cable landing station at West Beach has now reached the lock-up stage, a significant step forward in our build program. With the external structure, internal utilities and facility now secure, the project is moving confidently into the next phase of internal fitout to prepare for operational readiness. A huge thank you to our […]
Ile d’Yeu is continuing its progress towards Adelaide, with a long ~2,400km stretch of deep-water surface lay to complete, all in Lightweight Protected cable – read more about the different protection types used for SMAP linked here. Once she reaches the planned Adelaide branching unit location, she’ll bouy off the cable and carry out a […]