Monthly Archives: September 2024

Profile: Matt Row

Meet Matt Row

As Program Director at Soda, Matt Row leads the Land Access, Design, and Construction efforts for the SMAP project. With over 20 years of experience, Matt has collaborated with specialist contractors and consultants across all states and territories on a wide range of telecommunications infrastructure initiatives. His expertise has been instrumental in managing land access, […]

A visit to Equinix in Sydney

SUBCO team touring Equinix

While in town for the Sydney Groundbreaking event, the team visited the Equinix Data Centre in Sydney—a critical connection point for SMAP, where the new Sydney Cable connects to the Maroubra landing site and extends out to sea. Co-owners Bevan and Jodie Slattery, accompanied by Soda’s CCO Josh Munro, toured the facility which plays a […]

HDD has officially started in Maroubra

Today, the UEA team welcomed La Perouse LALC on-site to conduct a Cultural Heritage Induction and oversee the initial excavation at our HDD site in Maroubra. These inductions not only provide valuable insight into identifying culturally sensitive artefacts but also ensure clear consultation and communication with our stakeholders. Cultural heritage is something SUBCO has consistently […]

Watch this timelapse of the Sydney SMAP cable path

To celebrate the start of the Sydney portion of the SMAP build, we’re giving you a preview of the cable path – from Equinix Data Centre, to Maroubra Beach Manhole, and then beyond. The Horizontal directional drill (HDD) will be commencing this week which will run for a few months, while 8500 metres of new […]

Ground Breaking Event at Maroubra Beach

Sydney Ground Breaking Subco SMAP Blog

Last Wednesday, we gathered with our SMAP partners, including Randwick City Council, UGL, UEA, the La Perouse Aboriginal Community, and others, to celebrate the start of the Sydney portion of the SMAP cable build. It has been 15 Years since PPC-1 Landed in Sydney, which marks a special day for Bevan and Jodie Slattery coming […]

Cable manufacturing update from the team

SMAP Cable Manufacturing Update

PFE: For Perth , Sydney,  Adelaide and Torquay have been manufactured & tested Cable: 38% of the cable has been completed, with 2042 km out of 5265 km manufactured Repeaters: 71% completion, with 43 out of 60 repeaters manufactured and tested Branching Units: No progress yet on the manufacturing of Branching Units We also conducted a […]