On Friday 11 July, SUBCO had the honour of hosting the WA Premier, the Honourable Roger Cook; Minister for Resources, the Honourable Madeleine King; and the local Member for Cockburn, David Scaife MLA, for a tour of the mighty ASN cable-laying vessel Ile d’Yeu in Perth. We were also pleased to welcome industry friends, partners, […]
Tag Archives: Perth
Big things are happening off the coast of Perth! The mighty Ile d’Yeu is en route to deliver Australia’s very first undersea hypercable, SMAP. Originally built as a pipelayer back in 2001, Ile d’Yeu has since had a high-tech makeover, transforming into a top-tier cable-laying ship capable of installing some of the most advanced transoceanic […]
As we reach the mid-way point of 2025, SMAP continues to gain momentum, moving from planning and preparation into full-scale execution. This year has been marked by major achievements across regulatory approvals, system design, construction milestones, and now, the critical start of marine cable installation with the successful cable landing in Perth last week. With […]
This week marked a major moment for the SMAP project, with the successful shore-end landing of the cable system in Perth. The OMS shore-end and dive support teams were on site early to prepare for the landing. With the beach manhole and existing infrastructure ready, final checks were carried out on the seaward-facing conduit, which […]
The design for our Perth Cable Landing Station (CLS), housed within an existing data centre, was finalised last year, and is now underway. The CLS occupies approximately 40 square meters within the data centre, benefiting from all the “comforts of home”—including dual UPS and generator-backed electrical distribution systems, dual power feeds to every rack position, […]
PFE: For Perth , Sydney, Adelaide and Torquay have been manufactured & tested Cable: 38% of the cable has been completed, with 2042 km out of 5265 km manufactured Repeaters: 71% completion, with 43 out of 60 repeaters manufactured and tested Branching Units: No progress yet on the manufacturing of Branching Units We also conducted a […]
We are no stranger to Perth and when it comes to Fronthaul, we are well and truly ready to go. The Team’s at Diversified & Amstar are hard at work completing augmentation work on our already existing network to ensure the larger, fully armoured subsea cable system can be safely hauled. The team will be […]
Last week, members of the SUBCO team met with key stakeholders from Alcatel Submarine Networks and Optic Marine Systems in Perth to discuss progression of survey work, scheduling matters and terrestrial & subsea infrastructure interface. Coordination meetings are regularly held with delivery partners, including our subsea suppliers, to ensure smooth progression of the project and […]
Today, we had our Fibre Project Manager – Daniel Wright, undertake a manhole inspection for the cable landing preparation works in Perth. Surveys are crucial to ensure the proposed route is clear of obstructions and ensures the infrastructure has the capacity to handle the new cables. Inspections are done well before the cable arrives to […]