Backhaul Work Commences in Torquay

Torquay.backhual.blog

Exciting developments are taking place as backhaul work has officially commenced in Torquay! A SUBCO-approved contractor has begun the essential route feasibility study for the installation of sub-ducts and optic fibre cables along the primary path from Torquay to Melbourne. A key part of this process is the field walk exercise, which aims to determine […]

Bold Explorer completes deep sea survey

The Bold Explorer has completed the deep-sea survey journey from Perth to Adelaide, Melbourne, and Sydney. With over 5,000 nautical miles covered, we’ve been analysing seafloor sediments to determine the best path for the cable and assess seabed stability to prevent future movement or damage. Additionally, we evaluate the marine ecosystem to minimise our environmental […]

Grab sampling captured as inshore surveys approach completion.

As we near the completion of the final Inshore Survey off the shores of Torquay, our drone has captured some of the meticulous survey work being conducted. We are employing a variety of surveying methods, including a sub-bottom profiler, multi-beam echo sounder, and grab sampling. We’ve also captured footage of the grab sampling process in […]

Seagrass Survey Method – Adelaide

Seagrass.image

As part of the Marine survey activities, SUBCO has deployed an underwater camera to check the proposed cable alignment corridor to help plan the shallow water cable placement to minimise interactions with localised seagrass as much as possible as it traverses coastal waters off South Australia. Whilst working with South Australia Vegetation Council the team […]

Project Meetup with ASN & OMS

Smap.meetup

Last week, members of the SUBCO team met with key stakeholders from Alcatel Submarine Networks and Optic Marine Systems in Perth to discuss progression of survey work, scheduling matters and terrestrial & subsea infrastructure interface. Coordination meetings are regularly held with delivery partners, including our subsea suppliers, to ensure smooth progression of the project and […]

Inshore Survey Drone Flyover in Sydney

We organised a drone fly over at south Maroubra Beach to capture some of the survey work taking place in preparation for the Sydney landing. This site will provide a greater resilience for our international network as no other cables currently land here. This location is also preferred because the installation process is less likely to […]

SMAP Project Secures approvals for Marine Survey

Final consents and permits have been put in place for the Marine Survey component of the project. Over the past 6 months, SUBCO and its consultants have completed extensive Stakeholder consultations with Commonwealth and State based agencies in relation to the overall project and the specifics around the Marine Survey. The process included: Project briefings, […]