VicTrack backhaul hits 92% – Melbourne–Geelong rail corridor takes shape

The terrestrial backhaul connecting SMAP’s Melbourne (Torquay) landing to our PoPs is moving fast. We’re now at 92% completion – and the progress made over the couple of months reflects a serious team effort across design, permitting, procurement, and civil works. Routing backhaul through the VicTrack rail corridor delivers a geographically diverse, protected route that […]

Final testing at Torquay CLS & Melbourne DC underway

Construction may be finished, but before a system is declared ready for service, every fibre must pass rigorous validation. We’re now conducting final bi-directional Optical Time-Domain Reflectometer (OTDR) testing to ensure the entire span is performing exactly as engineered. OTDR testing allows us to measure fibre attenuation, splice integrity, and identify any reflections or anomalies […]

Backhaul cable install at Torquay CLS complete

Progress continues on the terrestrial backhaul infrastructure, with the cable installation into the Torquay CLS now completed. Our teams are currently undertaking cable terminations to prepare for the next stages of network integration. This milestone builds on earlier civil and conduit works and brings us closer to completing the terrestrial links needed for full connectivity. […]

Torquay West branching unit deployed

SMAP’s Torquay West branching unit (X-BU) has successfully made it into the water, marking another step closer to RFS for Australia’s first hypercable. The successful install connects Torquay with Adelaide and represents months of planning, coordination, and precision engineering, ensuring the cable is perfectly positioned for its next stage of deployment. The X-BU is a […]

VicTrack backhaul update

VicTrack back haul works along the Melbourne – Geelong rail corridor continues to make progress. Almost 85km of the 87km route has been walked and verified, 81km has now been rod and roped, and 50km of design has been completed and submitted, supporting sequencing and construction planning. Our delivery partners, CableNet Industries and FTS Resolve, […]

VicTrack backhaul progress

Last month we announced a partnership with the Victorian Government and VicTrack, to construct a fibre network along the Melbourne – Geelong rail corridor. Over the past couple months, the team have worked through challenging terrain, permitting, environmental considerations and extensive local stakeholder engagement – and the progress speaks for itself. To date, 80km of […]

SMAP cable makes landfall in Torquay

This week, the Ile d’Yeu successfully landed the eastern segment of the cable in Torquay, which will eventually connect to Sydney. Weather permitting, the team will land the western segment this week which will link all the way to Perth. To achieve this with minimal environmental impact, engineers installed two bore pipes running from a […]

Victoria connects to the SMAP network

SMAP continues to gather momentum, with the Victorian Government announcing its support for the new subsea hypercable that will directly connect Victoria to Australia’s next-generation digital backbone and beyond. As part of the Sydney-Melbourne-Adelaide-Perth (SMAP) system, this development marks a major step in extending world-class connectivity to Victoria’s south coast. The project will see two […]

Torquay fronthaul progress

We are pleased to share a significant milestone in our infrastructure rollout, with our contractor UGL, installing 903 metres of new conduit as part of the ongoing telecommunication works within Torquay. ​ Conduit and subducting plays a crucial role in protecting and guiding fibre cables, ensuring they are securely housed and easily accessible for future […]