As we reach the mid-way point of 2025, SMAP continues to gain momentum, moving from planning and preparation into full-scale execution. This year has been marked by major achievements across regulatory approvals, system design, construction milestones, and now, the critical start of marine cable installation with the successful cable landing in Perth last week. With […]
Tag Archives: Melbourne
Construction of the front haul network is now underway in Torquay, marking an important milestone for the project. Our contractor UGL Pty Ltd has commenced groundworks following the successful completion of land access negotiations with relevant stakeholders, including property owners, local council and utility providers. This collaboration has ensured that all necessary approvals […]
Exciting progress continues at the Torquay Cable Landing Station, with a significant milestone now achieved – the installation of all 49 internal and external walls, along with 38 hollow-core roof planks. This marks a pivotal step forward in the construction phase, as the facility begins to take on its final structural form. The installation of […]
Mobilisation has commenced at our Torquay sites for the next stage of the SMAP project, a significant step forward in the delivery of Australia’s first hyperscale subsea cable. UEA has begun preparing two key locations in Torquay, Victoria, in the lead up to construction works that will deliver the final ocean outfalls for SUBCO’s […]
Yesterday we held a historic event in Torquay, Victoria to mark the end of design and planning to build phase, for the first subsea cable in the state. Torquay being the last piece of the puzzle to complete for the SMAP cable, SUBCO’s 5,000km transcontinental, fully armoured subsea cable that will connect Sydney, Melbourne (Torquay), […]
Building a cable of this scale and complexity requires full visibility into progress and updates. To ensure this, some site locations have been equipped with aerial cameras to track developments and enhance security. Over the next few months, we’ll be sharing incredible time-lapse footage showcasing key locations as they reach completion. It’s a great way […]
A few weeks ago, we embarked on a critical assignment to assess the existing ducts for our planned route between Melbourne and Torquay. As we’ve emphasised before, our commitment to minimising environmental and community impact guides every decision we make, ensuring we always opt for the most efficient solutions. With the survey and rod and […]
Exciting developments are taking place as backhaul work has officially commenced in Torquay! A SUBCO-approved contractor has begun the essential route feasibility study for the installation of sub-ducts and optic fibre cables along the primary path from Torquay to Melbourne. A key part of this process is the field walk exercise, which aims to determine […]