Tag Archives: Construction

Adelaide CLS lock-up complete

The Adelaide cable landing station at West Beach has now reached the lock-up stage, a significant step forward in our build program. With the external structure, internal utilities and facility now secure, the project is moving confidently into the next phase of internal fitout to prepare for operational readiness. A huge thank you to our […]

Front haul works now underway at Torquay

Img 2818

Construction of the front haul network is now underway in Torquay, marking an important milestone for the project. ​ ​ Our contractor UGL Pty Ltd has commenced groundworks following the successful completion of land access negotiations with relevant stakeholders, including property owners, local council and utility providers. This collaboration has ensured that all necessary approvals […]

Adelaide CLS foundations in place

SUBCO construction site of Cable Landing Station with concrete slab poured

The Adelaide Cable Landing Station is now taking shape with another milestone reached with competition of the slab construction. ​ Our building contractor, Sagle, has worked diligently to bring us to this stage of the project. While the completed slab may appear minor at first glance, it represents a significant milestone – the successful completion […]

CLS construction commences in Adelaide

We’re excited to announce that construction is now officially underway on the Cable Landing Station (CLS) in West Beach – Adelaide, marking another critical milestone in the SMAP submarine cable project. The CLS site, located on a 20m x 20m block, has now been fully cut and prepared for the next phase of development. Bored […]

Adelaide cable landing station: Final design and upcoming construction

Subco.cls.adl

With the design finalised and approvals imminent, construction of our Adelaide Cable Landing Station is set to begin later this month. Originally designed to house just the Power Feed Equipment (PFE) and optical switching for backhaul to third-party data centres, the facility has now been expanded to accommodate Submarine Line Terminal Equipment (SLTE) deployment if […]

Site cut in Torquay kicks off CLS build

Construction has officially begun at our Torquay CLS site, with the site cut now in progress. Over the next eight months, we will be building this critical infrastructure, marking another major milestone in the SMAP project. A huge thank you again to our team for their dedication and hard work in bringing this project to […]

Why is BYDA Important?

Before You Dig Australia (BYDA) offers essential, free safety tools that allow users to locate and assess below-ground infrastructure, helping prevent accidental damage to critical assets. BYDA’s centralised data repository enables safe work practices and is invaluable for anyone planning excavation or construction projects SUBCO has integrated its assets into BYDA’s system, making it accessible […]

Sydney Fronthaul Construction is 50% Complete

Sydney Front Haul 50% Complete

We’re pleased to announce that over half of construction on our Sydney Fronthaul route is now complete. Our teams, including UGL and partners, have been hard at work around the clock, not only to ensure a safe and efficient build, but also to minimise any disruption to surrounding areas.  A big thank you to everyone […]

Watch this timelapse of the Sydney SMAP cable path

To celebrate the start of the Sydney portion of the SMAP build, we’re giving you a preview of the cable path – from Equinix Data Centre, to Maroubra Beach Manhole, and then beyond. The Horizontal directional drill (HDD) will be commencing this week which will run for a few months, while 8500 metres of new […]

Adelaide preparing for Beach Manhole excavation

Adelaide.hdd.completion

After a successful HDD completion, the team is now dismantling the rig in preparation for the Beach Manhole excavation works. Over the past week, we completed the final steps to conclude the HDD. These included verifying the offshore HDD exit with divers, testing and installing the messenger rope, which will ultimately be used to draw […]