We’re pleased to announce that over half of construction on our Sydney Fronthaul route is now complete. Our teams, including UGL and partners, have been hard at work around the clock, not only to ensure a safe and efficient build, but also to minimise any disruption to surrounding areas. A big thank you to everyone […]
Author Archives: Christian Sprenger
As manufacturing progresses, we’re excited to announce that (as of last week), the terminal equipment production has been marked as complete, with everything tested and officially signed off. This equipment will undergo further validation during System Assembly Testing (SAT), once all other system components are ready, before being shipped to site for installation in each […]
As part of the ongoing development of SMAP, our team of engineers have started to test various networking and facility management components thanks to a mock ‘lab’ set up in the SUBCO office. Security is paramount when it comes to the design of this system, so this testing process is key to ensure we have […]
Cultural heritage regulations and rules differ from state to state. For example, in South Australia, Aboriginal culture and heritage must be considered under the Aboriginal Heritage Act 1988 (SA). SUBCO engaged with local registered aboriginal parties in South Australia, and engaged third party experts to undertake due diligence at its Adelaide site before works commenced […]
With the completion of our work in Adelaide, we’re pleased to announce that West Beach Parks has formally approved the full reinstatement of our beach manhole site. As always, SUBCO is committed to working closely with local and cultural partners to ensure minimal environmental impact, full respect for cultural standards and reinstatement of sites to […]
We were proud to be a sponsor at this year’s Submarine Networks World Event in Singapore, which saw record-breaking attendance. Submarine Networks World is always a must on our events calendar each year, as it showcases the people and companies that are revolutionising the subsea space. Highlights included the SMAP model which was a centrepiece […]
As Program Director at Soda, Matt Row leads the Land Access, Design, and Construction efforts for the SMAP project. With over 20 years of experience, Matt has collaborated with specialist contractors and consultants across all states and territories on a wide range of telecommunications infrastructure initiatives. His expertise has been instrumental in managing land access, […]
While in town for the Sydney Groundbreaking event, the team visited the Equinix Data Centre in Sydney—a critical connection point for SMAP, where the new Sydney Cable connects to the Maroubra landing site and extends out to sea. Co-owners Bevan and Jodie Slattery, accompanied by Soda’s CCO Josh Munro, toured the facility which plays a […]
Today, the UEA team welcomed La Perouse LALC on-site to conduct a Cultural Heritage Induction and oversee the initial excavation at our HDD site in Maroubra. These inductions not only provide valuable insight into identifying culturally sensitive artefacts but also ensure clear consultation and communication with our stakeholders. Cultural heritage is something SUBCO has consistently […]
To celebrate the start of the Sydney portion of the SMAP build, we’re giving you a preview of the cable path – from Equinix Data Centre, to Maroubra Beach Manhole, and then beyond. The Horizontal directional drill (HDD) will be commencing this week which will run for a few months, while 8500 metres of new […]