Eighteen months ago, we sat down with SUBCO Founder Bevan Slattery to talk about why Australia needed a new kind of cable and the design of SMAP, and now, we’re on the final stretch to Ready for Service. Five thousand kilometres. Four capital cities. Australia’s first Hyper cable, fully armoured end-to-end, delivering over 400Tb/s of […]
Author Archives: Christian Sprenger
With the Adelaide Cable Landing Station (CLS) making excellent progress, we’re thrilled to announce the mobilisation for our Adelaide backhaul routes—marking another major milestone in the expansion of our network across South Australia. The back haul project will connect the CLS to the Adelaide CBD via two diverse routes, delivering greater resilience and capacity to […]
We’re pleased to share that the Horizontal Directional Drilling (HDD) works at Voss Circuit (Torquay) have been successfully completed, and the site was officially handed back to GORCAPA on 26 September 2025. Over the coming weeks, GORCAPA will carry out returfing and site restoration, preparing the reserve to reopen ahead of the busy summer season. […]
After the successful fit-outs of our Cable Landing Stations (CLS) in Perth and Sydney, our team set out once again—this time to Adelaide. With lessons learned from previous projects and a refined approach, we were ready to take on the next challenge. We’re back with SUBCO Senior Network Engineer – Rick Carter, who gives us […]
CLS install complete in Sydney After months of planning, we hit the ground running at Equinix SY5 to bring our new cage online. Over five days, our team – alongside a rotating cast of contractors – rolled in racks, configured systems, wired everything from LEDs to locks, and fine-tuned the security infrastructure. This blog, written […]
We’re excited to announce that construction is now officially underway on the Cable Landing Station (CLS) in West Beach – Adelaide, marking another critical milestone in the SMAP submarine cable project. The CLS site, located on a 20m x 20m block, has now been fully cut and prepared for the next phase of development. Bored […]
SUBCO, represented by Lee Harper, Carlos Trujillo, Bob Purdon, Matt Clancy, and Brendan Reddy, participated in the SMAP Contract Coordination Meeting (CCM) held in Sydney. Key stakeholders in attendance included representatives from ASN and OMS. The two-day event followed the standard CCM agenda. On the second day, attendees visited key project sites, including the Sydney […]
SUBCO has reached a major milestone in the SMAP subsea cable project, completing horizontal directional drilling (HDD) at Broadarrow Reserve in Maroubra. The time-lapse video captures weeks of engineering precision, community collaboration, and logistical coordination — condensed into 30secs. This stage of the project involved: Six successful horizontal directional drills, enabling safe and environmentally conscious […]
Construction at the Torquay Cable Landing Station site has reached a key milestone, with the main slab recently being poured. The slab is supported by 54 concrete piers, each drilled to a depth of 2.7 metres. Together, the slab and piers contain over 11 tonnes of steel reinforcement to provide structural strength. A total of […]
Recently, two of our team members – Rick Carter and Bob Purdon were on the ground in Perth working on the buildout of our first Data Centre site. With a tight schedule, multiple contractors, and a lot of hardware to install, it was a fast-paced and rewarding experience. In this post we take a bit […]