Adelaide cable landing station: Final design and upcoming construction

Subco.cls.adl

With the design finalised and approvals imminent, construction of our Adelaide Cable Landing Station is set to begin later this month. Originally designed to house just the Power Feed Equipment (PFE) and optical switching for backhaul to third-party data centres, the facility has now been expanded to accommodate Submarine Line Terminal Equipment (SLTE) deployment if […]

Before and After: Adelaide Drill Site Officially Reinstated

With the completion of our work in Adelaide, we’re pleased to announce that West Beach Parks has formally approved the full reinstatement of our beach manhole site. As always, SUBCO is committed to working closely with local and cultural partners to ensure minimal environmental impact, full respect for cultural standards and reinstatement of sites to […]

Cable manufacturing update from the team

SMAP Cable Manufacturing Update

PFE: For Perth , Sydney,  Adelaide and Torquay have been manufactured & tested Cable: 38% of the cable has been completed, with 2042 km out of 5265 km manufactured Repeaters: 71% completion, with 43 out of 60 repeaters manufactured and tested Branching Units: No progress yet on the manufacturing of Branching Units We also conducted a […]

Adelaide Manhole Installed

Manhole progress | SUBCO SMAP Blog

We’re excited to report that the beach manhole component in Adelaide has been completed.  Over the past 70 days, our construction partner CODMAH has put in significant effort to complete the challenging ocean lead-in, culminating in the installation of our custom-designed beach manhole. The ocean lead-in is a crucial segment of the cable route that […]

Adelaide preparing for Beach Manhole excavation

Adelaide.hdd.completion

After a successful HDD completion, the team is now dismantling the rig in preparation for the Beach Manhole excavation works. Over the past week, we completed the final steps to conclude the HDD. These included verifying the offshore HDD exit with divers, testing and installing the messenger rope, which will ultimately be used to draw […]

Adelaide drilling component has been completed

Great news from Adelaide! We have successfully completed the horizontal drilling component at the landing site, achieving a total distance of just over 1,000 meters. The next step is to verify the offshore HDD Exit with the diving team. The video above shows a timelapse of the drilling that took place in Adelaide. The HDD […]

HDD Construction Commences in Adelaide

Adl1

SUBCO has officially begun its Horizontal Directional Drilling (HDD) construction effort in Adelaide. Forming part of the Adelaide cable landing infrastructure, the 100mm ID HDD conduit will extend approximately 1000 meters from the shoreline and will break out under the surface at a depth of approximately 20 metres. For this HDD operation, a smaller pilot […]

Smoking Ceremony & Groundbreaking in Adelaide

Construction is underway! Wednesday 19th June, 2024, we turned the first sod on the new $400 million SMAP Cable in Adelaide with South Australia Minister for Trade and Investment, Joe Szakacs and the traditional owners the Kaurna people. SUBCO is excited to move into the construction stage of the 5,000 km new subsea transcontinental cable […]

Seagrass Survey Method – Adelaide

Seagrass.image

As part of the Marine survey activities, SUBCO has deployed an underwater camera to check the proposed cable alignment corridor to help plan the shallow water cable placement to minimise interactions with localised seagrass as much as possible as it traverses coastal waters off South Australia. Whilst working with South Australia Vegetation Council the team […]