Category Archives: SMAP Build

Why 5G Networks chose SMAP

Australia’s east coast is well-served. Sydney, Melbourne, Brisbane – competitive routes, multiple providers, reasonable pricing. Go west, and the picture changes. For Joe Damase, Managing Director of 5G Networks, that gap was a real problem. With 100Gbps waves running across Australia’s major capitals, PoPs in New Zealand, LA, Tokyo, and Singapore, and a growing Asia-Pac […]

Why Virtutel chose SMAP

Australia’s inter-capital network has a well-known problem. Terrestrial routes between east and west run in close proximity at multiple points – meaning a single incident can take out what operators assumed were independent paths. For Virtutel Managing Director & Founder David Allen, that’s not a theoretical risk. It’s the reason he chose SMAP. “There was […]

SMAP reaches provisional acceptance

After more than 1,000 days of surveying, manufacturing, installing, and testing, SMAP has reached provisional acceptance – the final validation milestone before the system is declared ready for service. It’s a significant moment. Provisional acceptance confirms that Australia’s newest transcontinental subsea cable system has been independently tested and verified to specification across its full 5,000-kilometre […]

SMAP: From vision to reality

Eighteen months ago, we sat down with SUBCO Founder Bevan Slattery to talk about why Australia needed a new kind of cable and the design of SMAP, and now, we’re on the final stretch to Ready for Service. Five thousand kilometres. Four capital cities. Australia’s first Hyper cable, fully armoured end-to-end, delivering over 400Tb/s of […]

Adelaide backhaul complete

SMAP’s backhaul network connecting the Adelaide CLS to the CBD is now complete, with final testing and commissioning well underway. Connecting the subsea and terrestrial networks, this milestone completes the end-to-end infrastructure chain that underpins SMAP’s connectivity offering in South Australia. With backhaul now in place, SMAP’s Adelaide infrastructure is ready for final system testing […]

Voss Circuit reinstatement complete

With the cooler, wetter weather arriving in Torquay, the final reinstatement activities at Voss Circuit are now complete. Over the past two weeks, the GORCAPA (Great Ocean Road Coast and Parks Authority) team carried out full area returfing – the last major step in restoring the site following SMAP’s cable landing works. The area will […]

VicTrack backhaul hits 92% – Melbourne–Geelong rail corridor takes shape

The terrestrial backhaul connecting SMAP’s Melbourne (Torquay) landing to our PoPs is moving fast. We’re now at 92% completion – and the progress made over the couple of months reflects a serious team effort across design, permitting, procurement, and civil works. Routing backhaul through the VicTrack rail corridor delivers a geographically diverse, protected route that […]

Final repeater deployed – marine install nearing finish line

SMAP marine installation has hit a landmark milestone with all 59 repeaters now in the water! With deployment of the final repeater, attention now turns to the final steps of marine installation. Next up is the Branching Unit (BU) integration at Torquay – connecting Melbourne (Torquay) and Sydney via the Torquay East X-BU – followed […]