Last month we announced a partnership with the Victorian Government and VicTrack, to construct a fibre network along the Melbourne – Geelong rail corridor. Over the past couple months, the team have worked through challenging terrain, permitting, environmental considerations and extensive local stakeholder engagement – and the progress speaks for itself. To date, 80km of […]
Category Archives: SMAP Build
Adelaide continues to make strong progress on the backhaul infrastructure works, with construction now nearing completion. Our contractor, Mirait, and their field teams have been working diligently across diverse terrain, to secure the optimal fibre path. A key focus has been verifying and proving the designated route to ensure full duct availability, clear passage, and […]
This week, the Ile d’Yeu successfully landed the eastern segment of the cable in Torquay, which will eventually connect to Sydney. Weather permitting, the team will land the western segment this week which will link all the way to Perth. To achieve this with minimal environmental impact, engineers installed two bore pipes running from a […]
SMAP continues to gather momentum, with the Victorian Government announcing its support for the new subsea hypercable that will directly connect Victoria to Australia’s next-generation digital backbone and beyond. As part of the Sydney-Melbourne-Adelaide-Perth (SMAP) system, this development marks a major step in extending world-class connectivity to Victoria’s south coast. The project will see two […]
The Torquay CLS continues to take shape following the final delivery of Alcatel Submarine Networks (ASN) equipment. In total, just over 6 tonnes of Power Feeding Equipment (PFE) will be installed at the site, marking a major milestone in preparing the station for the SMAP cable. Installation of the PFE has now commenced, ensuring the […]
We’re thrilled to be awarded ‘Best Subsea Innovation’ for SMAP by Capacity Media at last night’s Global Connectivity Awards in London! The awards celebrate the people and companies advancing the world’s digital infrastructure, bringing together industry leaders, innovators and investors in London each year to connect, collaborate and recognise global achievement. Thanks to Paddy Cunningham […]
The SMAP marine lay is progressing well, with more than 50% of the total cable length and repeaters now installed. This marks a major milestone in the build of Australia’s new east–west subsea connection. Following successful deep-water installation from Perth to Adelaide, plough burial has now commenced on the Adelaide branch. This process carefully embeds […]
The ASN team recently completed installation of the Power Feeding Equipment (PFE) for the SMAP cable at our Adelaide CLS. This equipment is a pivotal operational component of the system, and a major step closer to go-live for the project. PFEs provide constant high-voltage DC power to subsea repeaters, ensuring data travels reliably across thousands […]
With the Adelaide Cable Landing Station (CLS) making excellent progress, we’re thrilled to announce the mobilisation for our Adelaide backhaul routes—marking another major milestone in the expansion of our network across South Australia. The back haul project will connect the CLS to the Adelaide CBD via two diverse routes, delivering greater resilience and capacity to […]
We’re pleased to share that the Horizontal Directional Drilling (HDD) works at Voss Circuit (Torquay) have been successfully completed, and the site was officially handed back to GORCAPA on 26 September 2025. Over the coming weeks, GORCAPA will carry out returfing and site restoration, preparing the reserve to reopen ahead of the busy summer season. […]