A key piece of technology used on SMAP is the Full FIbre Drop Branching Unit (FFD BU). The FFD BU allows SMAP to flexibly service drops to an intermediate location off one fibre pair whilst allowing the other fibres to run “express” through. This reduces the latency caused by dropping in and out of all […]
Author Archives: Christian Sprenger
The submarine cable will be supplied and installed by Alcatel Submarine Networks. Also known as the wet segment, the submarine cable contains from 24 optical fibres which operate in pairs (12 pairs). The exact composition of the SMAP cable will vary along the route due to changing depths, laying methods and the risks associated with […]
After many months of route surveys, planning and contractor negotiations the SUBCO team have signed the first major fronthaul contract which will establish new conduit and manholes suitable to land the new SMAP cable. The large dimensions of the cable to be hauled require the manufacture of some custom made duct for the project. In […]
We organised a drone fly over at south Maroubra Beach to capture some of the survey work taking place in preparation for the Sydney landing. This site will provide a greater resilience for our international network as no other cables currently land here. This location is also preferred because the installation process is less likely to […]
Torquay CLS land acquired! After months of due diligence, SUBCO is now unconditional on the purchase of land for our Torquay CLS. Architects and engineering consultants are completing final touches on our CLS design for approval and commencement of construction. The focus is on security and resiliency, yet also being low impact in every aspect. […]
We’re pleased to announce that manufacturing has commenced, and the team at ASN are currently working on colouring the fibres individually. Fundamentally, this allows technicians to distinguish each cable – making it easier to splice and connect. To colour code optical fibres, an ultraviolet light-curable ink is mixed with a carrier fluid. This mixture is […]
The Torquay Cable Landing Station (CLS) is one of two CLS projects that SUBCO is developing from the ground up as greenfield sites. SUBCO has signed a contract of sale for land which is now unconditional following due diligence, which included: A review of any planning controls which constrain how the site may be used […]
Final consents and permits have been put in place for the Marine Survey component of the project. Over the past 6 months, SUBCO and its consultants have completed extensive Stakeholder consultations with Commonwealth and State based agencies in relation to the overall project and the specifics around the Marine Survey. The process included: Project briefings, […]
Today, we had our Fibre Project Manager – Daniel Wright, undertake a manhole inspection for the cable landing preparation works in Perth. Surveys are crucial to ensure the proposed route is clear of obstructions and ensures the infrastructure has the capacity to handle the new cables. Inspections are done well before the cable arrives to […]
Today, the Team was on the ground in Torquay, joined by surveyors, town planners, and construction contractors. They engaged in groundworks planning and design as part of our broader community-centric planning processes which play a crucial role in building Australia’s future. Whilst on site, the Team assessed site access for construction vehicles as well as […]