Tag Archives: Torquay

Voss Circuit reinstatement complete

With the cooler, wetter weather arriving in Torquay, the final reinstatement activities at Voss Circuit are now complete. Over the past two weeks, the GORCAPA (Great Ocean Road Coast and Parks Authority) team carried out full area returfing – the last major step in restoring the site following SMAP’s cable landing works. The area will […]

Backhaul cable install at Torquay CLS complete

Progress continues on the terrestrial backhaul infrastructure, with the cable installation into the Torquay CLS now completed. Our teams are currently undertaking cable terminations to prepare for the next stages of network integration. This milestone builds on earlier civil and conduit works and brings us closer to completing the terrestrial links needed for full connectivity. […]

VicTrack backhaul update

VicTrack back haul works along the Melbourne – Geelong rail corridor continues to make progress. Almost 85km of the 87km route has been walked and verified, 81km has now been rod and roped, and 50km of design has been completed and submitted, supporting sequencing and construction planning. Our delivery partners, CableNet Industries and FTS Resolve, […]

SMAP EOY update

Over the past quarter, SMAP has continued to advance across land and sea, with Adelaide and Torquay CLS fit outs progressing, backhaul mobilised, and the successful landing of Victoria’s very first subsea cable. Over 55% of the subsea cable is installed and the build is now at 85% overall completion.  Here’s a wrap-up of the project for this quarter:  Adelaide: CLS and backhaul progress The Adelaide CLS fit-out […]

SMAP cable makes landfall in Torquay

This week, the Ile d’Yeu successfully landed the eastern segment of the cable in Torquay, which will eventually connect to Sydney. Weather permitting, the team will land the western segment this week which will link all the way to Perth. To achieve this with minimal environmental impact, engineers installed two bore pipes running from a […]

Torquay CLS gears up with final ASN equipment delivery

The Torquay CLS continues to take shape following the final delivery of Alcatel Submarine Networks (ASN) equipment. In total, just over 6 tonnes of Power Feeding Equipment (PFE) will be installed at the site, marking a major milestone in preparing the station for the SMAP cable. Installation of the PFE has now commenced, ensuring the […]

Torquay HDD work complete and ready for returfing

We’re pleased to share that the Horizontal Directional Drilling (HDD) works at Voss Circuit (Torquay) have been successfully completed, and the site was officially handed back to GORCAPA on 26 September 2025. Over the coming weeks, GORCAPA will carry out returfing and site restoration, preparing the reserve to reopen ahead of the busy summer season. […]

Torquay fronthaul civils complete

All civil conduit and manhole works have now been successfully completed in Torquay, between the beach manhole and the cable landing station. The final stage of subduct installation is currently underway, marking one of the last key steps before we can transition into the next phase. This achievement is the result of months of coordinated […]

Morning meetings in Torquay

UEA, our Horizontal Directional Drilling contractor has added a fresh spin to their daily toolbox meetings – hosting them each morning at the Salty Dog Café. ​The morning ritual of breakfast and daily prestart check-in has quickly become part of their routine, creating a space where the team can connect, share updates, and start the […]