Category Archives: SMAP Build

Understanding Undersea: Torquay Landing to create a diverse connection into Melbourne CBD

SUBCO’s decision to establish a cable landing point in Torquay as part of the SMAP cable route heralds a significant development in bolstering connectivity between Torquay and Melbourne. By creating a diverse connection route, this strategic move enhances the resilience and reliability of communication networks through Geelong to the coast. Torquay’s coastal location further offers […]

Melbourne Backhaul survey and rod and roping complete

Torquay.backhual.blog

A few weeks ago, we embarked on a critical assignment to assess the existing ducts for our planned route between Melbourne and Torquay. As we’ve emphasised before, our commitment to minimising environmental and community impact guides every decision we make, ensuring we always opt for the most efficient solutions. With the survey and rod and […]

Adelaide preparing for Beach Manhole excavation

Adelaide.hdd.completion

After a successful HDD completion, the team is now dismantling the rig in preparation for the Beach Manhole excavation works. Over the past week, we completed the final steps to conclude the HDD. These included verifying the offshore HDD exit with divers, testing and installing the messenger rope, which will ultimately be used to draw […]

Adelaide drilling component has been completed

Great news from Adelaide! We have successfully completed the horizontal drilling component at the landing site, achieving a total distance of just over 1,000 meters. The next step is to verify the offshore HDD Exit with the diving team. The video above shows a timelapse of the drilling that took place in Adelaide. The HDD […]

Understanding Undersea: Unexploded Ordnance (UXOs)

Uxo.info.graphic

In Australia’s maritime territories, subsea cables cautiously manoeuvre around a captivating yet potentially hazardous underwater feature: Unexploded Ordnance (UXOs), remnants of historical naval activities. UXOs are the remnants of historical naval activities, scattered across the seabed. Australia’s coastal waters hold a trove of military history, where cable installation requires careful navigation to preserve both connectivity […]

Native vegetation reporting

A very important aspect of our SMAP build is respecting Country. We’re prioritising engagement with First Nations stakeholders and making sure to respect traditional knowledge and customs. Sometimes this looks like taking the time to be welcomed to Country, other times this means conducting thorough environmental impact assessments. Particularly, we are carefully planning our cable […]

SMAP will be Australia’s first fully armoured long-haul undersea cable

Da.cable.design

SMAP is poised to make waves in pioneering Australia’s first sully armoured subsea cable, representing a significant advancement in safeguarding critical communication infrastructure. The fully armoured design, adapted with varying levels of protection along different sections of the cable, offers unparalleled protection against potential threats and unplanned outages. Double Armour (DA) (pictured) adds two layers […]

HDD Construction Commences in Adelaide

Adl1

SUBCO has officially begun its Horizontal Directional Drilling (HDD) construction effort in Adelaide. Forming part of the Adelaide cable landing infrastructure, the 100mm ID HDD conduit will extend approximately 1000 meters from the shoreline and will break out under the surface at a depth of approximately 20 metres. For this HDD operation, a smaller pilot […]