Following last week’s site meet-up with Google, SUBCO are thrilled to announce the successful completion of HDD #2! Our delivery partner UEA have been making great progress, the video below illustrates divers finalising HDD #1 in Maroubra. During this process, precise measurements were taken to confirm positioning, including:• The distance from the seabed floor to […]
Category Archives: SMAP Build
Manufacturing of SMAP’s 61 repeaters has been completed, signalling a major milestone in the production of the cable system. During the manufacturing of the repeaters, over 25,000 tests/checks were carried out to ensure they meet specified performance criteria. Each repeater is placed 90km apart over the length of the cable and extensive testing and qualification […]
After thorough investigations and design work, we’re happy to announce that the Backhaul Path design from Torquay to Melbourne is now complete. This route will consist of 100km of new fibre that leads from our cable landing station (under construction) in Torquay, all the way to Melbourne CBD. The team have spent weeks meticulously selecting […]
Before You Dig Australia (BYDA) offers essential, free safety tools that allow users to locate and assess below-ground infrastructure, helping prevent accidental damage to critical assets. BYDA’s centralised data repository enables safe work practices and is invaluable for anyone planning excavation or construction projects SUBCO has integrated its assets into BYDA’s system, making it accessible […]
We’re pleased to announce that over half of construction on our Sydney Fronthaul route is now complete. Our teams, including UGL and partners, have been hard at work around the clock, not only to ensure a safe and efficient build, but also to minimise any disruption to surrounding areas. A big thank you to everyone […]
As manufacturing progresses, we’re excited to announce that (as of last week), the terminal equipment production has been marked as complete, with everything tested and officially signed off. This equipment will undergo further validation during System Assembly Testing (SAT), once all other system components are ready, before being shipped to site for installation in each […]
Cultural heritage regulations and rules differ from state to state. For example, in South Australia, Aboriginal culture and heritage must be considered under the Aboriginal Heritage Act 1988 (SA). SUBCO engaged with local registered aboriginal parties in South Australia, and engaged third party experts to undertake due diligence at its Adelaide site before works commenced […]
With the completion of our work in Adelaide, we’re pleased to announce that West Beach Parks has formally approved the full reinstatement of our beach manhole site. As always, SUBCO is committed to working closely with local and cultural partners to ensure minimal environmental impact, full respect for cultural standards and reinstatement of sites to […]
We were proud to be a sponsor at this year’s Submarine Networks World Event in Singapore, which saw record-breaking attendance. Submarine Networks World is always a must on our events calendar each year, as it showcases the people and companies that are revolutionising the subsea space. Highlights included the SMAP model which was a centrepiece […]
As Program Director at Soda, Matt Row leads the Land Access, Design, and Construction efforts for the SMAP project. With over 20 years of experience, Matt has collaborated with specialist contractors and consultants across all states and territories on a wide range of telecommunications infrastructure initiatives. His expertise has been instrumental in managing land access, […]