Watch: Time-lapse video of beach manholes being lifted into place

SUBCO’s works are progressing rain, hail or shine in Maroubra, with beach manholes now being installed and reinstatement well underway. Once the manholes are sealed early next week, UEA will complete returfing to restore the reserve to its original condition before handing it back to Randwick City Council. Check out the Time-Lapse video below!

Watching it all unfold in 4k

Building a cable of this scale and complexity requires full visibility into progress and updates. To ensure this, some site locations have been equipped with aerial cameras to track developments and enhance security. Over the next few months, we’ll be sharing incredible time-lapse footage showcasing key locations as they reach completion. It’s a great way […]

6th and final HDD signed off in Maroubra

Hdd.no6

Recently, we had the pleasure of signing off on the sixth and final HDD required for the Sydney (Maroubra) Landing. As mentioned in previous posts, the accuracy and precise measurements are critical before each HDD sign-off to ensure a smooth installation when the cable arrives later this year. This marks a significant milestone for the […]

Adelaide cable landing station: Final design and upcoming construction

Subco.cls.adl

With the design finalised and approvals imminent, construction of our Adelaide Cable Landing Station is set to begin later this month. Originally designed to house just the Power Feed Equipment (PFE) and optical switching for backhaul to third-party data centres, the facility has now been expanded to accommodate Submarine Line Terminal Equipment (SLTE) deployment if […]

CLS installation commences in Perth

The design for our Perth Cable Landing Station (CLS), housed within an existing data centre, was finalised last year, and is now underway. The CLS occupies approximately 40 square meters within the data centre, benefiting from all the “comforts of home”—including dual UPS and generator-backed electrical distribution systems, dual power feeds to every rack position, […]

Site cut in Torquay kicks off CLS build

Construction has officially begun at our Torquay CLS site, with the site cut now in progress. Over the next eight months, we will be building this critical infrastructure, marking another major milestone in the SMAP project. A huge thank you again to our team for their dedication and hard work in bringing this project to […]

SMAP obtains Commonwealth Environmental Approval

We have been given official approval from the Australian Government – Department of Climate Change, Energy, the environment and water, under the EPBC Act, for the installation our SMAP Cable. The EPBC (Environment Protection and Biodiversity Conservation) act is in place to Protect Australia’s environment, biodiversity, and cultural heritage by managing natural resources sustainably, assessing […]

HDD work in Sydney edges towards completion

Hdd.update.sydney.jan.25

HDD progress in Sydney advanced steadily over the holidays, with the successful completion of HDD3 and HDD4. Meanwhile, work on the 5th HDD is nearing completion, with just a few metres to go before punch-out. This is on track to be finalised by the end of this week. We would like to express our gratitude […]