While in town for the Sydney Groundbreaking event, the team visited the Equinix Data Centre in Sydney—a critical connection point for SMAP, where the new Sydney Cable connects to the Maroubra landing site and extends out to sea. Co-owners Bevan and Jodie Slattery, accompanied by Soda’s CCO Josh Munro, toured the facility which plays a […]
Category Archives: SMAP Build
Today, the UEA team welcomed La Perouse LALC on-site to conduct a Cultural Heritage Induction and oversee the initial excavation at our HDD site in Maroubra. These inductions not only provide valuable insight into identifying culturally sensitive artefacts but also ensure clear consultation and communication with our stakeholders. Cultural heritage is something SUBCO has consistently […]
To celebrate the start of the Sydney portion of the SMAP build, we’re giving you a preview of the cable path – from Equinix Data Centre, to Maroubra Beach Manhole, and then beyond. The Horizontal directional drill (HDD) will be commencing this week which will run for a few months, while 8500 metres of new […]
We invite you to take a closer look at our Sydney Groundbreaking Event. Watch as we take you to Maroubra Beach and hear a few words from SUBCO founder and SODA Infrastructure Co CEO, Bevan Slattery.
Last Wednesday, we gathered with our SMAP partners, including Randwick City Council, UGL, UEA, the La Perouse Aboriginal Community, and others, to celebrate the start of the Sydney portion of the SMAP cable build. It has been 15 Years since PPC-1 Landed in Sydney, which marks a special day for Bevan and Jodie Slattery coming […]
The SMAP Build has been immortalised in a miniature model and is on display at Ausnog 24. Comprising of 4,456 pieces and measuring in at 1.2 metres, the model features key components of the subsea build process, including the cable ship, survey ship, beach manhole and cable landing station.
PFE: For Perth , Sydney, Adelaide and Torquay have been manufactured & tested Cable: 38% of the cable has been completed, with 2042 km out of 5265 km manufactured Repeaters: 71% completion, with 43 out of 60 repeaters manufactured and tested Branching Units: No progress yet on the manufacturing of Branching Units We also conducted a […]
The design for our Torquay Cable Landing Station (CLS) has officially been approved and is scheduled to commence construction in the coming months. With a facility size of 258 square meters, the cable landing station comprises of 2 independent rooms, each equipped with its own uninterruptible power supply (UPS) and cooling systems. Plus, two un-interrupted […]
We’re excited to report that the beach manhole component in Adelaide has been completed. Over the past 70 days, our construction partner CODMAH has put in significant effort to complete the challenging ocean lead-in, culminating in the installation of our custom-designed beach manhole. The ocean lead-in is a crucial segment of the cable route that […]
As we reach the one-year mark on the SMAP project, we sat down with Bevan to get his perspective on the last twelve months and an insight into what’s on the horizon. “I’m excited to share some key updates. It’s been a busy and challenging year, with this project standing out due to its scope […]